Skip to content.
Sections
Home About Us Consumer Industry Contact Vacancies
Document Actions

Part D Review Project

The Electricity Commission (Commission) is running a project to carry out a fundamental review of part D of the Electricity Governance Rules 2003 (Rules).

Part D of the Rules sets out the obligations on participants in relation to metering standards. It deals with the responsibility of participants in relation to the provision of metering installations, the testing of metering installations, ensuring a metering installation complies with a set of codes of practice, and the role of the reconciliation manager in relation to metering inaccuracies.

Background

The Commission has established a project (Part D Review) to carry out a fundamental review of part D of the Rules.  The Part D Review has come about because:

  1. the existing set of rules in part D is internally inconsistent, references out of date international standards, is in part ambiguous, and has a general lack of clarity.  This is not an appropriate compliance regime for a system that handled $6.4 billion in wholesale market trades in 2008;
  2. New metering and communications technology has emerged and the current part D rules are inadequate for dealing with it.  In some instances, the existing rules act as a barrier to the innovation opportunities presented by this new technology. In other cases, the absence of any regulatory framework leaves the consumer exposed to potential breaches of security in relation to the accuracy, security and privacy of information related to billing.  Associated with new technology, a new regulatory framework is required that will enable:
    1. future developments such as smart grids (allow consumers to interact with the electricity market);
    2. multiple participants and the consumer to interface with the metering installation (the current rules envisage only one participant interfacing with the metering installation);
    3. the ability for retailers to offer different tariff options, enhanced load management options and markets etc; and
    4. enable electricity supply alternatives, which includes demand side management.  

Initial consultation on Part D: Issues and possible options

In late 2008 the Commission consulted with the industry about undertaking a fundamental review of the existing regulatory framework for metering in the New Zealand electricity industry, as contained in part D of the Rules, to ensure that it is fit for purpose.  The consultation sought the industry’s feedback on the key issues identified with the rules contained in part D, options to address these key issues, and suggested guiding principles for a review of part D.

The industry’s submissions confirmed the issues and options detailed in the consultation document, and confirmed the suggested scope of the Part D Review. Consequently, the Commission established the Part D Review Project.

Project purpose

The purpose of the Part D Review project is to:

  1. fix the problems with the current rules;
  2. Update the current rules to allow for and keep pace with the adoption of new metering technology; and
  3. future proof the rules to enable innovation.

Implementation of any new regulatory framework will proceed only after substantial consultation with the industry and provided any recommendations to the Minister for rule changes are approved. 

If and when any rule changes are approved the Commission anticipates running an implementation project at that point to ensure the new regulatory framework is implemented in an appropriate timeframe and in a coordinated manner.

Project Scope:

The project will:

  1. review the existing regulatory framework for metering as contained in part D of the Rules to ensure that it is fit for purpose; and 
  2. examine the market developments in metering and infrastructure to determine what, if any, impact these developments have on the regulatory framework contained in part D and develop proposed rules, where necessary, to manage impacts that cannot be left to guidelines to ensure:
    1. metering technology does not become a barrier to customer switching;
    2. technology being currently installed is appropriate;
    3. information is secure and privacy is maintained;
    4. AMI complements the current load management infrastructure; and
    5. open access to metering information is achieved.

The part D rules structure document pdf [14 KB] contains the extent of the rules being reviewed.

Project structure

The governance for the project is being provided by a Steering Committee.  This group also proactively provides quality management and assurance of the deliverables over the life of the project.

The key project work is being carried out by a specialist Project Team, to work through the issues and options arising out of the August 2008 consultation, on the Part D review.  The outputs produced by the Project Team were subject to a peer review by an Industry Reference Group (IRG)

The output from this process is being used as the basis of the proposed new rules principles, to be consulted on. 

Industry Reference Group

The IRG provided unbiased and expert knowledge to the Commission by:

  1. considering the options proposed by the four work streams and advise on the impact of the proposed changes on the industry; 
  2. providing advice/feedback on other possible options for achieving the outcome; 
  3. providing advice on technical matters; 
  4. providing advice, at a high level, on the likely benefits and costs of the proposed changes;
  5. providing an assessment of costs and benefits for options determined during the review process; and
  6. determining options that may not have been previously considered.

Project Timeline

The Part D Review project is expected to take approximately 20 months to complete. The key stages are outlined in the following table:

Project Stage Timeline Status
      Stage 1: Consultation & Project Approval
1
Initial Consultation, and Board Approval August - December 2008
Complete
     Stage 2: Planning and Project Establishment
2 Planning and Project Establishment January - February 2009 Complete
     Stage 3: Issues and Options Investigation (new rules principles developed)
3 Development of options to address the issues identified from the August consultation February - July 2009 Complete
4 Reviewing these options with an industry reference group
May - July 2009
Complete
     Stage 4: Consultation on Proposed New Rules Principles
5 Development of proposed options, based on the options identified. This includes consideration of both regulatory and non-regulatory solutions (consultation preparation) July - September 2009 Complete
6 Board approval of proposed new rules principles September 2009 Complete
7 Consultation with industry Late September - November 2009 In progress
8 Industry forum to introduce the proposed options 30 September 2009 Confirmed
9 Review submissions and seek Board approval to commence new rules principles drafting November - December 2009 Pending item 7 above
     Stage 5: Rules Drafting & Consultation
10 New regulatory framework development (Rules drafting) December 2009 - April 2010 Pending item 9 above
11
Consultation on proposed new regulatory framework
May - June 2010
Pending item 10 above
12 Board Approval of proposed new regulatory framework August - September 2010 Pending item 11 above
     Stage 6: Rules Approval
13
New regulatory framework approval process (with Minister)
September - October 2010
Pending item 12 above
      Stage 7: Project Closure
14
Project completion
October - November 2010
Pending stage 9 above

Industry forum

An industry forum was held on 30 September 2009 to introduce the proposed new rules principles (consultation on part D issues and proposed options)

Commission contact

If you have any questions regarding the project, please contact Todd Collings on todd.collings@electricitycommission.govt.nz or 04 462 0602.

Last update on 06 October 2009 01:57 PM