Final decision


This page includes the Commission's final decision in respect of Transpower's North Island Grid Upgrade Proposal (Proposal) and various documents that the Electricity Commission (Commission) considered in making its decision.

Background


Public conference (May 2007)

On 31 January 2007, the Commission issued a notice of its intention to approve the Proposal in accordance with rule 15.1 of the Electricity Governance Rules 2003 (Rules). In accordance with rule 15.2, a number of persons requested that the Commission hold a public conference in relation to the Proposal. The purpose of a public conference is to provide interested persons with a final opportunity for comment on the Proposal. The Commission agreed to hold a public conference.  The public conference was held in May.

Additional information received following public conference (June 2007)

During the public conference, a number of presenters indicated that they would provide further information relating to their oral submissions made at the conference. Information from the following parties was received:
  • Regis Park Stage 2 Limited
Additional advice sought (June 2007)

In light of the issues raised in submissions, the Commission engaged a specialist property valuer (Graeme Horsley Limited), to review the earlier work of The Property Group and consider property related concerns raised in submissions. 
Commission requests for further information and Transpower responses (May 2007– June 2007)

Final summary of further work (July 2007)

The Commission has also prepared a short document that summarises its final further work completed since the public conference.
This document is additional to the summary of further work pdf [94 KB] published on 15 May 2007.

Final decision


The Commission has decided (by a majority) to confirm its decision to approve the Proposal. 

The documents below set out the final decision of the Commission (by majority) to confirm its approval of Transpower’s North Island Grid Upgrade Proposal.
This document explains key aspects of the context and background to the decision, as well as the decision itself. It is not intended to be comprehensive and it is provided for information only.
This document sets out in detail the reasons for the Commission's decision to confirm its approval of the Proposal.
  • Minority opinion
Commissioner Pinnell has confirmed his dissent from the majority and has provided an updated minority opinion.