Transpower submitted a new grid upgrade plan to the Electricity Commission on 17 December 2008 (2008 GUP). The 2008 GUP contains, among other things :
- A comprehensive plan for asset management and operation of the grid;
- Information on investment contracts; and four investment proposals.
Part 1 and 2 - Comprehensive Plan for Asset Management and Investment Contracts
Part 3 – Wairakei Ring Investment Proposal
Part 4 - Maungatapere Bus Security Investment Proposal
Part 5 - Wellington 110kV Interconnection Investment Proposal
Part 6 – Woodville-Mangamaire-Masterton Transmission Investment Proposal
Part 7 - Bombay Bus Security Investment Proposal
Part 8 – Redclyffe Bus Security Investment Proposal
Part 9 - Marsden Substation Investment Proposal
Part 10 - Redclyffe 220/110kV Interconnection Investment Proposal
Last update on