Grid Upgrade Plan 2005
Transpower submitted the GUP to the Electricity Commission on 30 September 2005. The GUP can be found on Transpower’s website and it contains, among other things :
- A comprehensive plan for asset management and operation of the grid;
- Information on investment contracts; and
- Four investment proposals:
- Proposed North Island 400kV grid upgrade from Whakamaru-Otahuhu
- A plan to upgrade the HVDC inter-island link
- Central North Island Thermal Upgrade Project involving a number of circuit upgrades to central North Island circuits; and
- Bunnythorpe-Haywards Thermal Upgrade Project
On 20 October 2006, Transpower submitted an amendment to its proposed North Island grid upgrade.
Grid Upgrade Plan 2005
- Volume 1
- Volume 2 (North Island Grid Upgrade Project)
- Volume 3 (HVDC Pole 1 Replacement Proposal)
- Volume 4
Volume 1
Volume 2 (North Island Investment Proposal)
- 20 October 2006 proposal
- 20 October 2006 letter from Transpower pdf [104 KB]
- Transpower North Island Supply Upgrade Application pdf [651 KB]
- A Diversity Analysis for UNI pdf [90 KB]
- B Treatment of the ARI-PAK Line pdf [69 KB]
- C Delivery Risk Report pdf [162 KB]
- D Technical Assesment of Modified Options pdf [1131 KB]
- E Economic Analysis of Alternatives pdf [394 KB]
- F Costing Report pdf [82 KB]
- G High Temperature Conductor Report pdf [153 KB]
- H1 Timing of Auckland Supply Upgrade GUP Proposal pdf [86 KB]
- H2 Pre-Augmentation EUE Assessment pdf [278 KB]
- I Duplexing Report pdf [333 KB]
- J Assumptions List pdf [67 KB]
- K Economic Analysis of Non Transmission Alternatives pdf [136 KB]
- L Transpower Discount Rate for GIT Report pdf [243 KB]
- M Assessment of the Value of Unserved Energy pdf [139 KB]
- N Foreign Direct Investment Effects pdf [396 KB]
- Original proposal
Volume 3 (HVDC Pole 1 Replacement Proposal) - withdrawn
- Executive Summary pdf [49 KB]
- Introduction pdf [38 KB]
- Part I: Project Description and Project Plan pdf [114 KB]
- Part II: Establishing the Need for Investment pdf [670 KB]
- Part III: Analysis of Options for Meeting the Investment Need pdf [142 KB]
- Part IV: Cost Benefit Analysis pdf [192 KB]
- Part V: Project Costs pdf [80 KB]
- Supporting documents
- HVDC Pole 1 Condition and Risk Assessment pdf [729 KB]
- Pole 1 Replacement Options (part by part replacement) pdf [190 KB]
- HVDC Development Options – Cable Capacity pdf [41 KB]
- Peer review of HVDC economics analysis pdf [176 KB]
- HVDC AC switchyard report pdf [20733 KB]
- Methodology to Calculate the Lower Bound of Competition Benefits pdf [27 KB]
Correspondence
- Commission's letter dated 21 October 2005 PDF [287 KB]
- Transpower's letter dated 8 December 2005 PDF [199 KB]
- Transpower's letter dated 27 February 2006 PDF [138 KB]
- Commission's letter dated 8 March 2006 PDF [284 KB]
- Transpower's response dated 13 March 2006 PDF [1458 KB]
- Commission's response dated 4 May2006 PDF [348 KB]
- Transpower's letter dated 26 May 2006 PDF [322 KB]
- Commission's letter dated 22 June 2006 PDF [342 KB]
On 2 May 2008, Transpower submitted a revised HVDC proposal as part 5 of the 2007 GUP and withdrew the 2005 HVDC application.